Project Surveying for the M5 (East) Tunnel Fitout

BHBB M5 East Joint Venture

Start: June 2000

Project Surveyors: Pier Tilocca (Bexley Rd), Bill McClatchie (Marsh St)

Supervising Surveyor: Ross Robinson

Ross Robinson Surveys was engaged as consultant surveyors for the M5 East tunnel fit-out works in June 2000. Since that time we have been supplying project support surveys for tunnel fit-out construction from both the Bexley Road & Marsh Street portals.

On the 30th April 2001 breakthrough occurred in the Westbound tunnel, followed by breakthrough in the Eastbound tunnel on 21st March 2001.

The surveyed misclose tolerances achieved at the breakthrough interface were in the order of 15mm in chainage, 20mm in offset & 10mm in height. The final survey adjustment of the total tunnel control (both eastbound & westbound) was made using least-squares techniques.

The project has since been completed, with the M5 East tunnel officially opened to the public on the 9th of December 2001.

We are currently in the process of finalizing our contract with BHBB M5 East JV by backing up construction data files, 'Works as Executed' documentation and transmittals, and volumetric analysis.

Homestead Estate, Yamba Road, Yamba

East Coast Pty Limited

Start: May 2001

Project Surveyor: Bob Moyle

Registered Surveyor: Ross Robinson

Surveryors Assistant: Paul Goyma

138-142 Barcom Ave, Darlinghurst - Multi-level residential apartments building

Austin Arenco Pty Limited

Start: March 2001

Project Surveyor: William McClatchie

Registered Surveyor: Ross Robinson

On the 13th March, Ross Robinson Surveys was engaged to supply professional surveying services to the Barcom Road, Darlinghurst development currently being constructed by Austin Arenco Pty Limited.

The site occupies approximately 1400m2 of prime inner-city real estate, fronting both Barcom Avenue and Boundary Street, Rush Cutters Bay. The proposed development calls for the construction of a multi-storey residential development, compromising 5 levels of apartments over basement car parking and commercial units.

Our services to date include:

  • Survey control to site (MGA94 & AHD).
  • Cadastral boundary definition, marking of corners and survey report.
  • Site co-ordination, Civilcad modelling of architectural layouts, boundaries and grid line network, upload GSI set-out files to TCA1500L automated total station for field set-out.
  • Set-out geo-cast walls along Barcom Avenue frontage.

The basement and lower floors, up to level 4 have been completed. Work is progressing on the 5th and final level, with structural concrete due for completion in January 2002. Fitting out of the units will commence in the new year. Our ongoing involvement in the project will mainly consist of cadastral surveys and 'works as executed' documentation.

Static GPS Control Survey - M5 East Motorway 'As Built' documentation

BHBB M5 JV

Start: November 2001

Project Surveyor: Bill Mc Clatchie

Registered Surveyor: Ross Robinson

This project called for a 28km GPS levelling from Picnic Point, West Sydney, to Erskinville, inner city. The GPS observations were made using static method with observation times of approximately 30mins.

*******Ross Robinson Surveys were engaged to provide project support surveying for the entire project********.

Our services to date include:

  • Cadastral boundary definition & pegging of the site prior to construction.
  • Computer aided drafting (CAD) & digital terrain modelling (DTM). Upload digital design data to Leica TCA1100 total station for field set-out.
  • Engineering surveying - set-out & control of all civil works (bulk earthworks, drainage, roadworks, conveyors, buildings, bored concrete piles, etc).
  • Conformance reporting & "Works as Executed" documentation.
  • Cadastral survey & preparation of plan of electrical easement for registration with the Land Title Office.

Transgrid Cable Route, Picnic Point to Erskinville

Diona Pty Limited

Start: October 2001

Project Surveyor: Ross Robinson

Registered Surveyor: Ross Robinson

This project called for a 28km GPS leveling from Picnic Point, West Sydney, to Erskinville, inner city. The GPS observations were made using static method with observation times of approximately 30mins.

*******Ross Robinson Surveys were engaged to provide project support surveying for the entire project********.

Our services to date include:

  • Cadastral boundary definition & pegging of the site prior to construction.
  • Computer aided drafting (CAD) & digital terrain modeling (DTM). Upload digital design data to Leica TCA1100 total station for field setout.
  • Engineering surveying - setout & control of all civil works (bulk earthworks, drainage, roadworks, conveyors, buildings, bored concrete piles, etc).
  • Conformance reporting & "Works as Executed" documentation.
  • Cadastral survey & preparation of plan of electrical easement for registration with the Land Title Office.

Windsor Road - Re-alignment and Widening, Western Sydney, NSW

NACE Civil Engineering Pty Limited

Start: July 2001

Project Surveyor: Rob Friend

Consulting Surveyor: Ross Robinson

Our services to date include:

  • Assist with overall design.
  • Established site survey control network.
  • Engineering surveys - setout and control of all piling works.
  • Conformance surveys and QA verification reporting.
  • Works as Executed documentation of completed products.

The project is due for completion at the start of 2002.

Nelsons Ridge Estate (stage 4),Greystanes

Daracon

Start: March 2004

Project Surveyor: William McClatchie

Registered Surveyor: Ross Robinson

Field Assistant: Richard Arnell

In March 2004 Ross Robinson Surveys commenced work for Daracon Engineering to detail the Works As Executed documentation for the Nelsons Ridge Estate (Stage 4) at Greystanes.

Our services included:

  • Extensive use of GPS RTK to acquire bulk field data for works as executed documentation
  • Conformance and "Works as Executed" reporting
  • Computer aided drafting (CADD) & digital terrain modelling (DTM) utilising 12D model and AutoCAD software
  • Preparation of fare drawings and electronic product transmittals
  • Certification by registered surveyor Ross Robinson